That job in Phoenix where we hit solid rock 8 inches down on every single post hole for a 200-foot run

We had to switch from the auger to a jackhammer attachment, which added 2 full days to the schedule and completely blew the budget, so what's your go-to plan when you hit unexpected rock - do you eat the cost and power through, or stop and renegotiate the contract with the client?
4 comments

Log in to join the discussion

Log In
4 Comments
jennifer833
Ever try to price in a rock clause upfront? Spencer_park26's story is exactly why I always do now.
7
spencer_park26
Remember when bedrock ate our backhoe bucket.
5
rubyk26
rubyk261mo ago
Honestly, I've been there too @spencer_park26. Best move is to just tell the client upfront that you're not eating that cost if you hit something you can't see. Saves a lot of headaches later.
7
daniel140
daniel1403mo ago
Read about rock clauses saving jobs like that.